IN THE Black Canyon of the Colorado, where the river forms the boundary between the states of Arizona and Nevada, the Government of the United States through the Department of the Interior and directly by the Bureau of Reclamation has started construction of Hoover Dam.

On September 17, 1930, constructional activities were formally inaugurated by Secretary of the Interior Ray Lyman Wilbur, and since that date, under the supervision and control of the Bureau of Reclamation, headed by Commissioner Elwood Mead, the building of the dam has progressed rapidly. Construction operations are carried out under the direction of R. F. Walter, Chief Engineer of the Bureau of Reclamation, represented in the field by the writer.